Major Wind Park in Dalarna

Nordisk Vindkraft is building a wind park containing ten turbines at Kyrkberget in Dalarna. Tyréns has performed the geotechnical survey and prepared the accompanying reports and material for the project.

We also ensured that the Swedish adaptations to Eurocode were taken into account when dimensioning the foundation. We were responsible for the quality controls according to the Swedish Planning and Building Act (PBL) and we assisted with the building permit application process. Nordisk Vindkraft hired us to act as the construction managers in order to guarantee the legal requirements for finished parts. Aside from this we have also led assignments for the general ground and road contractors to dimension and create the ground foundations for road construction and subsequent bearing tests as part of the control programme.

Orderer:Nordisk Vindkraft